Balluku announced it on August 2, but the government hid the extension of the works for the Arbri road for 2 years

Balluku announced it on August 2, but the government hid the extension of the

The Minister of Infrastructure and Energy, Belinda Balluku, announced on August 2 the postponement of the works deadline for the Arbri road by 17 months.

According to Balluk, geological problems are the reason for the postponement of the deadline.

"The Murriz tunnel remains to be delivered, which has put us in front of a very big difficulty in terms of geology and we had to look at the whole project," Balluku declared in a public event.

The Arbri road contract, expected to be delivered in April 2020, is expected to be completed in September 2023. Although Balluku announced the postponement of the works deadline 9 days ago. actually the deadlines have been changed since 2020.

According to the data that BIRN has obtained from the Ministry of Infrastructure, the project for the Murriz tunnel and the deadline for the delivery of the road has been changed to 2020, which has been kept secret by the government for two years.

The construction of the 54-kilometer road connecting Tirana with Dibra began in 2018.